The EDEKA store will open on 14.03.2024
Construction site report
The EDEKA store will open on 14.03.2024, which means that a large part of the project has been completed. The remaining construction work is in its final stages. The outdoor facilities and open spaces are already 50% complete. The windows and entrance doors are 90% installed. The natural stone work in the stairwells is 90% complete. The metalwork is 50% complete, as is the painting work.
The EDEKA store will open on 14.03.2024
Construction site report
The EDEKA store will open on 14.03.2024, which means that a large part of the project has been completed. The remaining construction work is in its final stages. The outdoor facilities and open spaces are already 50% complete. The windows and entrance doors are 90% installed. The natural stone work in the stairwells is 90% complete. The metalwork is 50% complete, as is the painting work.
The EDEKA store will open on 14.03.2024
Construction site report
The EDEKA store will open on 14.03.2024, which means that a large part of the project has been completed. The remaining construction work is in its final stages. The outdoor facilities and open spaces are already 50% complete. The windows and entrance doors are 90% installed. The natural stone work in the stairwells is 90% complete. The metalwork is 50% complete, as is the painting work.
The EDEKA store will open on 14.03.2024
Construction site report
The EDEKA store will open on 14.03.2024, which means that a large part of the project has been completed. The remaining construction work is in its final stages. The outdoor facilities and open spaces are already 50% complete. The windows and entrance doors are 90% installed. The natural stone work in the stairwells is 90% complete. The metalwork is 50% complete, as is the painting work.
The EDEKA store will open on 14.03.2024
Construction site report
The EDEKA store will open on 14.03.2024, which means that a large part of the project has been completed. The remaining construction work is in its final stages. The outdoor facilities and open spaces are already 50% complete. The windows and entrance doors are 90% installed. The natural stone work in the stairwells is 90% complete. The metalwork is 50% complete, as is the painting work.
The EDEKA store will open on 14.03.2024
Construction site report
The EDEKA store will open on 14.03.2024, which means that a large part of the project has been completed. The remaining construction work is in its final stages. The outdoor facilities and open spaces are already 50% complete. The windows and entrance doors are 90% installed. The natural stone work in the stairwells is 90% complete. The metalwork is 50% complete, as is the painting work.
The EDEKA store will open on 14.03.2024
Construction site report
The EDEKA store will open on 14.03.2024, which means that a large part of the project has been completed. The remaining construction work is in its final stages. The outdoor facilities and open spaces are already 50% complete. The windows and entrance doors are 90% installed. The natural stone work in the stairwells is 90% complete. The metalwork is 50% complete, as is the painting work.
The EDEKA store will open on 14.03.2024
Construction site report
The EDEKA store will open on 14.03.2024, which means that a large part of the project has been completed. The remaining construction work is in its final stages. The outdoor facilities and open spaces are already 50% complete. The windows and entrance doors are 90% installed. The natural stone work in the stairwells is 90% complete. The metalwork is 50% complete, as is the painting work.